With the weather cooperating more than usual for the middle of February, crews are making good progress on the Butler Senior High School construction project.
The Butler Area School District Board of Directors heard an update at their Monday night meeting from the district’s construction manager on the classroom expansion project.
The Board approved several change orders totaling nearly $78,000 involving adding a duct coil to temperature controls in the guidance area as well as additional support in the existing 300 wing to support a new piece of equipment being added to the roof there.
Crews are starting painting work this week with delivery of lockers expected later in the week. Installation of outside panels is expected for next week. The finished rooms are still scheduled to be turned over to school faculty and staff in late March.